Rezoning Approved

On March 25, 2026, City Council approved the rezoning of 4025 Parliament Avenue to support future commercial development. With the rezoning complete, work can now begin on the design for underground services (water, sewer and storm sewer) that will be shared between the commercial development and the expanded Rawlinson Crescent Park.

This drawing shows the circular park space and a conceptual layout for the commercial land around it.

Design work and tendering of underground services will occur in late 2026, as will marketing and the sale of the commercial land. Tendering and construction of the underground services are expected to be complete by the end of June 2027. This timing aligns with the planned construction of the park which will begin in late spring 2027 and extend into Fall 2027 or Spring 2028, depending on weather.